Klabin has started operating a new recovery boiler supplied by Valmet at its Monte Alegre mill in Telêmaco Borba, Paraná, Brazil. The unit entered service on October 15, 2026, 47 days ahead of the original schedule.
The new boiler replaces Recovery Boiler 1, which had been operating since 1978, and has a capacity of 1,950 tonnes of dry solids per day.
The installation is part of a R$1.7 billion modernization project launched in July 2024 to support the mill's operational continuity, efficiency and competitiveness.
According to Klabin's third-quarter 2026 results, the company invested R$511 million in the Monte Alegre modernization project during the first nine months of 2026, against a full-year investment guidance of R$700 million.
Recovery boiler and chemical recovery systems
Valmet's scope of supply included the recovery boiler, an ash crystallization plant with a processing capacity of 140 tonnes per day, and a non-condensable gas (NCG) handling system for collecting and handling odorous gases.
The ash crystallization plant is designed to remove chloride and potassium from the chemical recovery cycle, helping reduce corrosion and ash accumulation in the boiler. The system is intended to support longer operating periods and lower maintenance requirements.
Automation and process optimization
The delivery also included a comprehensive automation and process optimization package, featuring Recovery Boiler Optimizer, Green Liquor Quality Optimizer and Ash Balance Optimizer applications.
Other technologies include a Recovery Ash Analyzer for online monitoring of ash composition, boiler diagnostic systems and Valmet Training Simulators.
Energy efficiency and environmental improvements
The modernization project also incorporates new electrostatic precipitators for atmospheric emissions control and a 100-meter-high stack.
The new boiler is designed to improve steam and energy generation through more efficient processing of black liquor, a byproduct of pulp production, reducing the mill's reliance on supplementary fossil fuels and increasing the share of renewable energy in its energy mix.
In addition to the new recovery boiler, the project includes upgrades to the control and operating systems in the recovery, utilities and fiber areas, including the replacement of the existing distributed control system with a new generation of technology.