Arauco has raised approximately US$410 million through the placement of a sustainable hybrid bond, as the Chilean forestry and pulp producer takes further steps to strengthen its financial position ahead of the startup of its US$4.6 billion Sucuriú mill in Brazil.
The company placed UF 10 million on November 6. The bond has a maturity of 32 years and three months and an interest rate of 4.13%, with a spread of 163 basis points over the reference rate. Demand reached 1.45 times the amount offered.
This is Arauco's second hybrid bond issuance in approximately one year. In October 2025, the company placed UF 20 million in its first sustainable hybrid bond issue.
Broader financial measures
The latest transaction forms part of a broader set of financial measures outlined by Arauco to prepare its balance sheet for the Sucuriú startup. These include a US$200 million capital increase, US$320 million in asset sales, the extension of a US$450 million credit line, and a commitment from parent company Empresas Copec to contribute up to US$450 million between 2027 and 2028.
CFO Gianfranco Truffello said the issuance was part of a series of decisions aimed at ensuring that Arauco reaches the startup of Sucuriú with a solid balance sheet.
The hybrid bond is subordinated to Arauco's senior debt. It allows the company to defer interest payments at its discretion and cannot be prepaid before the seventh year.
Sucuriú project reaches 84.3% completion
Located in Inocência, in the state of Mato Grosso do Sul, Sucuriú is designed to produce 3.5 million tonnes of bleached hardwood kraft pulp (BHKP) annually. In its November 2026 Q3 results presentation, Arauco reported that overall project progress had reached 84.3% as of October 30, 5.9 percentage points ahead of schedule.
Electromechanical erection stood at 47%, 16 percentage points ahead of plan, while engineering and procurement were nearly complete. The 230 kV transmission line and main substation transformer had also been completed.
Valmet, which is supplying the mill's key process islands and automation systems, reported further installation milestones in September. These included the lifting of the 300-tonne recovery boiler steam drum, completion of the hydrostatic tightness test for the fiberline downflow tower, and progress on the pulp drying building, where a 75-tonne overhead crane had been tested.
Arauco continues to target startup in the fourth quarter of 2027.